South Pars Oil Layer

South Pars Oil Layer

Scope of this project was the EPCI package for the Offshore Wellhead Platform (890 T) and its jacket (3200 T) that was signed between PEDCO and SAFF on 12th of Dec 2006. In the first phase of this project 7 wells will produce 35,000 bpd of oil. An FPSO will be used for the production and processing. The pre-commissioning hookup for this project was done on 1st of Jun 2015. SAFF has also been in charge of the commissioning phase of this project. South Pars Oil Layer is using a FPSO for the production. The FPSO arrived in the location and the production was started in Mar. 2017.

tug 2017 04 09 13 03 34

 

Project Summary

  Location

  South Pars Gas Field
  Client   PEDCO
  Duration   12 months
  Start Date   Feb. 2006
  Completion Date   Jul. 2015
  Scope   EPCI package for an Offshore Wellhead Platform and Related Jacket

 