A+ A A-

Construction of the tank, surrounding wall, industrial buildings and access road sweeping of the desalination plant of Bandar Abbas

 

Project Summary  
Location  Bandar Abbas 
Client  Asia Water Engineering Company 
Duration  24 months 
Value(MUSD)  19.9 
Start Date  June 2016 (On Going) 
Scope 

Construction of Tank : 64 tousands m3

Civil Works: Construction of wall of the site, industrial Buildings 

 des960908 1  des960908 3  des960908 2